2011 - Replaced existing boiler with two new condensing boilers for improved energy efficiency. Installed new circulation pumps. Installed new digital controls. Replaced unit ventilators. Installed new digital thermostats.

2009 - Roof and selected windows replaced on the Annex Building, and insulation was installed in the floors, attic and walls. New carpet and tiles in classrooms, hallways and auxiliary rooms. Covered walkway connected portable with main building. Window roller shades were replaced and classroom door hardware compliant with ADA regulations was installed. Mechanical upgrades included rehabilitation of existing classroom heaters, relief hoods and convectors.