BTA IV » Webster School » Planning & Construction Updates and Photos

Planning & Construction Updates and Photos

 

January 2019

  • Responded to second round of comments from Seattle Department of Construction and Inspections.
  • Received bids on mechanical, electrical, demolition and other packages.


November 2018

  • Responded to all permit review comments and resubmitted to city
  • Dewatering Authorization Application submitted
  • Elevator bid package and demolition bid package prepared for advertising 
  • Final Landmarks ARC and Board presentation scheduled 


October 2018

  • Received all permit review comments
  • Completed site infiltration test
  • Completed constructability review
  • Received 98% estimates


September 2018

  • Held site improvement plans (SIP) meeting 
  • Completed 98% construction documents


August 2018

  • Permit review comments have been received.
  • Master Use Permit process completed with no appeals received.
  • Performed 65% Construction Design drawing and budget reviews.
  • Coordination with Landmarks Preservation Board to allow replacement of historic windows began
  • The design team reviewed window mock ups.
  • Existing conditions were verified including determining wall types and verifying hazardous materials locations.


June 2018

  • Received the final departure report issued by the City of Seattle on June 13
  • Submitted the 60% construction documents for permitting on June 26 as scheduled  
  • Facilities department obtaining permits for pruning the street trees as required by City of Seattle arborists


April 2018

  • Held second Departures meeting on April 30 
  • Performed more investigation on existing wall types 
  • Met with Landmarks ARC (Architectural Review Committee) on April 27 to review gymnasium design elements 
  • Continued window condition survey for 1930s building 
  • Began surveying building for hazardous materials 
  • Continued work on construction documents


March 2018

  • Nordic Heritage Museum relocated to their new location 
  • Toured building to see existing conditions 
  • Design Development approval letter sent to Architect to start construction documents


Return to Webster School